🕐04.05.09 - 22:29 Uhr
i-minerals press release May 4, 2009
QUARTERLY FEASIBILITY AND PERMITTING UPDATE
ON KELLYS BASIN FELDSPAR QUARTZ DEPOSIT
Vancouver, B.C.
(May 4, 2009) -- i-minerals inc.
(TSX.V: IMA, the Company)
i-minerals provides the following update with respect to ongoing permitting
and feasibility activities.
Feasibility
SRK Consulting (US) Inc.
(SRK), is directing the feasibility study (the
FS) for i-minerals Kellys Basin feldspar-quartz deposit located near
Bovill, Idaho.
When completed, the FS will forecast all elements of the
project to an expected accuracy of 15%.
The FS will be reviewed by
financial institutions as part of their due diligence for project financing.
A NI 43-101 compliant summary document will be filed on SEDAR upon
completion of the study.
Principal elements of the project currently being
addressed for the FS are the final mine plan, completion of the haul road
design and mine waste dumps, contract mining costs, infrastructure needs,
and hydrologic modeling of dewatering the pit.
* The final mine plan will be completed once the final design of the
stream diversion that will run around the edge of the pit is completed.
* Geotechnical work and preliminary design of the haul road and mine
waste dumps are complete with approval of the final reports still pending.
* Initial bids for the mine activity (stripping, mining, haulage and
road maintenance) have been received from mining contractors, while mine
infrastructure needs are being assessed and planned.
* A water well was drilled in the mine area last October and a pump
test was run out of this well.
Data from this test, monitoring data from the
two piezometers, and hydrogeological data collected in the Moose Creek
watershed will be used in modeling the hydrology in order to finalize the
water balance within the mine area and to determine any surrounding effects
of dewatering the pit during mining.
The results of the modeling are not
only needed for determining water control operating costs at the mine and
water needs at the plant, but also to support the application for the water
rights permit.
Plant Design
The pilot plant run on a 5-ton sample produced from drill core has been
completed, leading to the completion of the process flow sheet.
Based on the
pilot plant information, schematics of each circuit have been drawn and
water balances calculated.
This information will be used in the engineering
construction design once the plant site location is finalized.
The geotechnical work for the plant foundation and tailings impoundment and
preliminary process design in which an engineering contractor will develop a
conceptual layout of the plant including the tailings area, will start once
the plant and tailings impoundment sites have been finalized as discussed
below.
Permitting
Tetra Tech, Inc.
(TetraTech) is the consulting company contracted by
i-minerals inc.
responsible for the environmental assessments and
permitting.
As last reported, the US Army Corps of Engineers (the Corps)
is the lead regulatory agency in the primary permitting and environmental
evaluation process.
Upon the completion of the public comment, additional
information was requested including (i) more detailed design of the stream
diversion around the pit, (ii) the final pit configuration in relation to
the reclamation plan, and (iii) the specific location of the plant and
tailings impoundment.
As noted above, the final design of the stream
diversion is nearing completion.
The final location of the plant and tailings impoundment is delaying the
completion of the mine plan and the Section 404 Wetland Permit Application.
The most favorable prospective location for both the plant and tailings
impoundment is land controlled by the State of Idaho previously disturbed by
mining that is contiguous with i-minerals mineral leases.
This location
hosts a depleted open pit from prior clay mining operations that might be
used as the tailings impoundment.
After filling with tailings, the ground
could be restored to the original approximate contour level and then
reclaimed.
There is additional area around this previously disturbed mine
area to place a plant without having to deforest large areas.
Other
potential mill and tailings facility locations would necessitate cutting
timber on larger portions of the State lands and require the use of longer
segments of public roads.
Based upon these attributes and other benefits to regional stakeholders,
i-minerals has made application to the Idaho Department of Lands (the IDL)
to gain access to this favorable location.
i-minerals has made detailed
presentations to both the IDL and the Idaho Land Board staff.
The Company
is confident this favored location offers the best logistics, and minimizes
certain environmental factors; however, the Idaho Department of Lands
continues to review the application and these delays have prevented access
to the most favored site for purposes of environmental evaluation, which in
turn, has caused the Corps to place its permit review and environmental
evaluation process on hold pending the Idaho Department of Lands leasing
decision It is difficult to accurately predict the associated timeframe to
conclude this process.
i-minerals inc.
per: Roger Kauffman
Roger Kauffman,
President & CEO
Contact:
i-minerals inc.
Encompass Communications Inc.
Barry Girling
877-303-6573 or 604-303-6573
877-566-6592 or 604-630-0770
Email:
Or visit our website at www.imineralsinc.com
Email:
The TSX Venture Exchange has not reviewed and does not accept responsibility
for the adequacy or accuracy of this release
This News Release includes certain "forward looking statements" within the
meaning of the United States Private Securities Litigation Reform Act of
1995.
Without limitation, statements regarding potential mineralization and
resources, exploration results, and future plans and objectives of the
Company are forward looking statements that involve various risks.
Actual
results could differ materially from those projected as a result of the
following factors, among others: changes in the world wide price of mineral
market conditions, risks inherent in mineral exploration, risk associated
with development, construction and mining operations, the uncertainty of
future profitability and uncertainty of access to additional capital.
Subject to applicable laws, the Company assumes no obligation to update or
revise any forward-looking statement, whether as a result of new
information, future events or any other reason.