Fortbridge Media ReleaseBlackthorn Resources Ltd [BTR] - MUMBWA PROJECT: Phase 5 Drilling Progress ReportBlackthorn Resources provide a progress report for Phase 5 drilling activities being undertaken at the Mumbwa Project in Zambia.
Two drilling rigs are progressing planned Phase 5 targets.
The first drill hole, S36-023 has been completed at 481.28m and the drill rig is preparing to mobilise and commence drilling regional scout holes.
The second hole, S36-024 is at approximately 320m drilled depth.
A third drilling rig has been ordered to supplement drilling progress. Delivery expected next week.