Dear all,
Please find below an announcement made today regarding the commencement
of a PFS on Heap Leaching for Phase 2 Growth at the Companys wholly
owned Mkuju River Project in southern Tanzania.
Mantra Resources Limited (Mantra or Company) (ASX:MRU, TSX:MRL) is
pleased to announce that it has commenced a Pre-Feasibility Study
(PFS) on heap leaching lower grade mined ore at the Companys Mkuju
River Project (MRP or the Project) for the Projects second phase of
growth.
Phase 1 of the Project, which is currently the subject of the Companys
Definitive Feasibility Study (DFS), is targeting approximately 3.7
million pounds of uranium a year using the Resin-in-Pulp (RIP)
metallurgical process.
It is envisaged that Phase 2, the heap leaching
of lower grade mined ore, would commence after the RIP circuit has
reached steady state operations and provide the Project with an
incremental increase in production over and above the targeted annual
production rate of Phase 1.
The commencement of the Heap Leach PFS follows positive results from
initial heap leach testwork campaigns conducted at the ANSTO and SGS
facilities in Australia.
The initial testwork clearly demonstrated that
the low grade ore is particularly amenable to heap leaching.
The results
of column testwork, which simulates a heap leaching process, were very
encouraging, indicating a uranium recovery rate of approximating 80% in
eight days with a low acid consumption of approximately 8 kilograms per
tonne.
No other reagents were required to achieve final recoveries.
Mantra believes there is the opportunity for a low cost, incremental
increase in production through the recovery of additional uranium from
the lower grade (less than the current resource cut-off grade of 200 ppm
U3O8) material which is currently being mined and treated as waste in
the pit optimisation process for Phase 1.
The capital expenditure for
this Phase 2 growth is anticipated to be modest.
Peter Breese, CEO, commented "We are very excited about the opportunity
that heap leaching lower grade, mined material offers to further
maximise the value of our business through incremental production growth
at low capital and operating cost.
We have decided to proceed with the
PFS for Phase 2 growth now in order to ensure key aspects of the heap
leach can be incorporated during the construction of Phase 1."
The Heap Leach PFS is due to be completed during the first quarter of
2011 and will include further resource modelling and detailed leaching
testwork to allow grade/recovery relationships to be investigated, the
minimum cut-off grade for economic treatment of the Nyota orebody to be
determined and additional data for engineering, design and costing to be
generated.
Upon successful completion of the Heap Leach PFS, it is
planned to progress to a DFS, which will include extensive integrated
metallurgical testwork and an updated Environmental Impact Statement.
Please dont hesitate to contact Peter Breese, Robert Behets or Alex
Buck if you have any questions.
Regards
Peter Breese
Chief Executive Officer
<